CBA Project

Franklin Yards

The project consists of a historic redevelopment of three buildings on the south side of Franklin Blvd: a former YWCA on W 31st, a historic mansion on W32nd, and a small, 2,000 SF one-story building immediately south of the mansion, and (2) ground up multifamily construction on the north side of Franklin Blvd. The Co-Developer is working with and anticipates putting a breakfast/lunch restaurant in the small commercial building. The buildings all surround a courtyard space, which will be highly landscaped and include common area amenities. Other building amenities include a fitness center, community living room, and work/study living room.

About the Developer & Project

  • President: Neil Viny
  • Primary Contractor: White Label Const.

Redevelopment Project 3105 Franklin Blvd 44113

  • Start Date: July 1, 2024
  • End Date: April 1, 2025
  • Total Project Cost: $19,104,203
  • Total Hard Construction Cost: $15,552,478

Funds

  • CRA Tax Abatement (CD) - $5,072,963.12
  • TIF (ED) – $1,966,331.97
  • Equity Inv: $6,092,774
  • Bank Loans: $10,200,000
  • Dollar Bank tax credit equity investment: $2,811.429

Building(s): (3)

  • Parcels: 00331063, 00331004, 00332001 
    YWCA – 31 residential units 
    Mansion – 7 units 
    New Construction – 29 units

Community Benefits Agreement Terms

  • MBE Participation Goal (15%)
  • FBE Participation Goal (7%)
  • CSB Participation Goal (8%)

Cleveland Resident Construction Worker Hours: 20% Requirement

Low-Income Cleveland Resident Construction Worker Hours: 4% of the 20% Requirement

Mentor/Protégé Program: (3) Mentor/Protégé Relationships

Apprenticeships: (3) Cleveland/ resident apprentices

Internships: (2) Cleveland Resident Interns at the Rate of $20 /hr. for a minimum of 50 hrs. worked per intern

Community Engagement: (3) Community Stakeholders’ meetings